Project Management Professional (PMP) Exam Practice – Question0044 The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as: A. exploit B. avoid C. mitigate D. share Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0043Project Management Professional (PMP) Exam Practice – Question0045