Project Management Professional (PMP) Exam Practice – Question0050 A risk that arises as a direct result of implementing a risk response is called a: A. contingent risk B. residual risk C. potential risk D. secondary risk Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question0049Project Management Professional (PMP) Exam Practice – Question0051