Project Management Professional (PMP) Exam Practice – Question0052 A tool and technique used in the Develop Project Charter process is: A. change control tools B. expert judgment C. meetings D. analytical techniques Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0051Project Management Professional (PMP) Exam Practice – Question0053