A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
A. Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan
A. Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan