Project Management Professional (PMP) Exam Practice – Question0055

The process of defining how the project scope will be validated and controlled is known as:


A.
Define Scope.
B. Develop Project Management Plan.
C. Plan Scope Management.
D. Plan Quality Management.

Correct Answer: C