The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
A. Earned value management.
B. Forecasting.
C. Critical chain methodology.
D. Critical path methodology.
A. Earned value management.
B. Forecasting.
C. Critical chain methodology.
D. Critical path methodology.