Project Management Professional (PMP) Exam Practice – Question0064

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?


A.
Information management systems
B. Work performance reports
C. Stakeholder analysis
D. Data gathering and representation

Correct Answer: A