Project Management Professional (PMP) Exam Practice – Question0072

Which process is included in the Project Integration Management Knowledge Area?


A.
Manage Project Team
B. Collect Requirements
C. Sequence Activities
D. Direct and Manage Project Work

Correct Answer: D