Project Management Professional (PMP) Exam Practice – Question0075

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:


A.
Historical information and the lessons-learned database.
B. Historical information and the stakeholder register.
C. Organizational process assets and the lessons-learned database.
D. Project documents and historical information.

Correct Answer: A