Project Management Professional (PMP) Exam Practice – Question0085 Which of the following risk response strategies involves allocating ownership of a positive risk to a third party? A. Mitigate B. Transfer C. Share D. Avoid Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0084Project Management Professional (PMP) Exam Practice – Question0086