Project Management Professional (PMP) Exam Practice – Question0088

What is a hierarchically organized depiction of the identified project risks arranged by risk category?


A.
Risk register
B. Risk breakdown structure (RBS)
C. Risk management plan

D. Risk category

Correct Answer: B