Project Management Professional (PMP) Exam Practice – Question0091

Organizations perceive risks as:


A.
events that will inevitably impact project and organizational objectives.
B. the effect of uncertainty on their project and organizational objectives.
C. events which could have a negative impact on project and organizational objectives.
D. the negative impact of undesired events on their project and organizational objectives.

Correct Answer: B