Organizations perceive risks as:
A. events that will inevitably impact project and organizational objectives.
B. the effect of uncertainty on their project and organizational objectives.
C. events which could have a negative impact on project and organizational objectives.
D. the negative impact of undesired events on their project and organizational objectives.
A. events that will inevitably impact project and organizational objectives.
B. the effect of uncertainty on their project and organizational objectives.
C. events which could have a negative impact on project and organizational objectives.
D. the negative impact of undesired events on their project and organizational objectives.