Who selects the appropriate processes for a project?
A. Project stakeholders
B. Project sponsor and project stakeholder
C. Project manager and project team
D. Project manager and project sponsor
A. Project stakeholders
B. Project sponsor and project stakeholder
C. Project manager and project team
D. Project manager and project sponsor