Project Management Professional (PMP) Exam Practice – Question0094

The Verify Scope process is primarily concerned with:


A.
formalizing acceptance of the completed project deliverables.
B. accuracy of the work deliverables.
C. formalizing approval of the scope statement.
D. accuracy of the work breakdown structure (WBS).

Correct Answer: A