Project Management Professional (PMP) Exam Practice – Question0109

Plan Risk Management is the process of defining how to:


A.
Communicate identified risks to the project stakeholders.
B. Conduct risk management activities for a project.
C. Analyze the impact a specific risk may have on the project.
D. Address unexpected risks that may occur during a project.

Correct Answer: B