Project Management Professional (PMP) Exam Practice – Question0116

The project scope statement and resource calendars are inputs to which Project Time Management process?


A.
Sequence Activities
B. Estimate Activity Resources
C. Develop Schedule
D. Control Schedule

Correct Answer: C