Project Management Professional (PMP) Exam Practice – Question0117

Which process determines the risks that might affect the project?


A.
Perform Qualitative Risk Analysis
B. Identify Risks
C. Plan Risk Management
D. Perform Quantitative Risk Analysis

Correct Answer: B