Project Management Professional (PMP) Exam Practice – Question0119 Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work? A. WBS directory B. Activity list C. WBS D. Project schedule Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0118Project Management Professional (PMP) Exam Practice – Question0120