Project Management Professional (PMP) Exam Practice – Question0124

In which process is a project manager identified and given the authority to apply resources to project activities?


A.
Acquire Project Team
B. Develop Project Management Plan
C. Manage Project Execution
D. Develop Project Charter

Correct Answer: D