Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
A. Requirements traceability matrix
B. Work breakdown structure (WBS) dictionary
C. Requirements management plan
D. Requirements documentation
A. Requirements traceability matrix
B. Work breakdown structure (WBS) dictionary
C. Requirements management plan
D. Requirements documentation