Project Management Professional (PMP) Exam Practice – Question0143

Which of the following correctly explains the term "progressive elaboration'?


A.
Changing project specifications continuously
B. Elaborate tracking of the project progress
C. Elaborate tracking of the project specifications with a change control system
D. Project specifications becoming more explicit and detailed as the project progresses

Correct Answer: D