Project Management Professional (PMP) Exam Practice – Question0149

Project contracts generally fall into which of the following three broad categories?


A.
Fixed-price, cost reimbursable, time and materials
B. Make-or-buy, margin analysis, fixed-price
C. Time and materials, fixed-price, margin analysis
D. Make-or-buy, lump-sum, cost-plus-incentive

Correct Answer: A