Project Management Professional (PMP) Exam Practice – Question0154

Which of the following is a project constraint?


A.
Twenty-five percent staff turnover is expected.
B. The technology to be used is cutting-edge.
C. Project leadership may change due to volatile political environment.
D. The product is needed in 250 days.

Correct Answer: D