Project Management Professional (PMP) Exam Practice – Question0172

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:


A.
operate separately.
B. move together in batches,
C. overlap and interact.
D. move in a sequence.

Correct Answer: C