Project Management Professional (PMP) Exam Practice – Question0174

Which of the following response strategies are appropriate for negative risks or threats?


A.
Share, Accept, Transfer, or Mitigate
B. Exploit, Enhance, Share, or Accept
C. Mitigate, Share, Avoid, or Accept
D. Avoid, Mitigate, Transfer, or Accept

Correct Answer: D