Project Management Professional (PMP) Exam Practice – Question0177

Risk responses reflect an organization's perceived balance between:


A.
risk taking and risk avoidance.
B. known risk and unknown risk.
C. identified risk and analyzed risk.
D. varying degrees of risk.

Correct Answer: A