Project Management Professional (PMP) Exam Practice – Question0182

Which statement correctly describes the value of a business case?


A.
It provides the necessary information to determine if a project is worth the required investment.
B. It provides for alternative dispute resolution procedures in event of contract default.
C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
D. It is used to help a project manager understand the scope of commercial advantages.

Correct Answer: A