Project Management Professional (PMP) Exam Practice – Question0183

Which of the following includes how requirements activities will be planned, tracked, and reported?


A.
Configuration management plan
B. Scope baseline
C. Requirements management plan
D. Schedule baseline

Correct Answer: C