The probability and impact matrix is primarily used to:
A. Quantify risk issues for trends during a quality audit.
B. Develop a risk register for risk planning.
C. Evaluate each risks importance and priority during Perform Qualitative Risk Analysis.
D. Define risk and compare impacts during Perform Quantitative Risk Analysis.
A. Quantify risk issues for trends during a quality audit.
B. Develop a risk register for risk planning.
C. Evaluate each risks importance and priority during Perform Qualitative Risk Analysis.
D. Define risk and compare impacts during Perform Quantitative Risk Analysis.