Project Management Professional (PMP) Exam Practice – Question0198

Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?


A.
Schedule Control
B. Activity Definition
C. Schedule Development
D. Activity Resource Estimating

Correct Answer: D