Project Management Professional (PMP) Exam Practice – Question0218

In the Initiating Process Group, at what point does the project become officially authorized?


A.
When the project charter is signed
B. When all the stakeholders agree on the scope of the project
C. When the project manager is appointed
D. When the necessary finance or funding is obtained

Correct Answer: A