Project Management Professional (PMP) Exam Practice – Question0233

During a projects initiation phase, the project manager reviews the business case and finds that information is incomplete. What should the project manager do?


A.
Add an information gap to the risk register.
B. Review the project statement of work (SOW) to create the project charter.
C. Revise the business case to narrow the project scope and create the project charter.
D. Review the business case with the sponsoring organization to confirm that the project aligns with business needs.

Correct Answer: D