A project has been initiated that has several project stakeholders from various departments. Some stakeholders are unavailable for the facilitation meeting to discuss end-to-end processes. To satisfy their own personal agenda, the project owner requests that the
meeting take place without all stakeholders present.

What should the project manager do?


A.
Reschedule the meeting to accommodate all stakeholders.
B. Hold a separate meeting with those stakeholders who are unavailable.
C. Set up a facilitation meeting without all stakeholders to obtain initial requirements.

D. Discuss stakeholder availability with the sponsor.

Correct Answer: D