Project Management Professional (PMP) Exam Practice – Question0237

After joining a new project, the project manager discovers that stakeholders initial expectations of its duration fail to match their own experience with rolling out similar projects. What should the project manager do?


A.
Present the stakeholders with lessons learned from prior projects.
B. Ask the project sponsor for additional resources.
C. Revise the duration estimates to meet stakeholder expectations.
D. Update the project scope to align with stakeholder requirements.

Correct Answer: A