The procurement department submits a request for proposal (RFP) to potential vendors to execute a project. After the bidder conferences, the project manager receives an email from vendor A requesting clarification of the RFP.
What should the project manager do next?


A.
Amend the RFP with the clarification and resend it to all the vendors.
B. Email all the vendors with the clarification.
C. Email vendor A with the clarification.
D. Obtain managements approval before sending the information.

Correct Answer: D