Project Management Professional (PMP) Exam Practice – Question0240

A key stakeholder misses a project kick-off meeting. The project manager arranges a separate meeting to ensure that the stakeholder understands that the projects expected business value aligns with the organizations strategy.
What are the key areas that should be reviewed?


A.
Cost, schedule, risks, and work breakdown structure (WBS)
B. Goals, objectives, benefits, and risks
C. Benefits, effort, and resources
D. Schedule, benefits, and WBS

Correct Answer: B