Project Management Professional (PMP) Exam Practice – Question0241

During a project meeting, a stakeholder disagrees with a key deliverable and project milestone listed in the approved project charter. What should the project manager have done to prevent this?


A.
Engaged the stakeholder earlier
B. Classified stakeholders using a power/interest grid
C. Met more frequently with the stakeholder
D. Conducted a thorough stakeholder analysis

Correct Answer: D