A project manager is working on a complex project with multiple team members and sponsors. What should the project manager do before obtaining project approval and buy-in?
A. Complete a stakeholder analysis
B. Meet with the stakeholders.
C. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
D. Perform a risk analysis.
A. Complete a stakeholder analysis
B. Meet with the stakeholders.
C. Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
D. Perform a risk analysis.