An experienced project manager is preparing a kick-off meeting for a new service assessment. A high-level description of the service has been provided.
What should the project manager do next?


A.
Develop the project charter.
B. Develop the responsible accountable, consult, and inform (RACI) matrix.
C. Define the project scope statement.
D. Create the work breakdown structure (WBS).

Correct Answer: C