A project manager has only a short timeframe in which to complete a projects cost estimation. What estimating technique should the project manager use?
A. Top-down
B. Three-point
C. Bottom-up
D. Analogous
A. Top-down
B. Three-point
C. Bottom-up
D. Analogous