Project Management Professional (PMP) Exam Practice – Question0249

Company A wants to subcontract the installation of a factorys building management system to company B. After some adjustments and a review of key stakeholder feedback, company Bs project manager needs to develop the project charter for approval.
What should company Bs project manager consider as an input when developing the project charter?


A.
Subcontractor submittal approval
B. Letter of intent
C. Submission of project management plan
D. Letter of enquiry

Correct Answer: B