Project Management Professional (PMP) Exam Practice – Question0253

Company A hires a project manager for Company Bs new project. What document does the project manager need from company B to develop the project charter?


A.
Scope statement
B. Statement of work (SOW)
C. Work breakdown structure (WBS)
D. Project management plan

Correct Answer: B