Project Management Professional (PMP) Exam Practice – Question0254

A project manager must obtain approval for a network cabling project. After preparation of detailed information, some team members remain dissatisfied, as the selected equipment is new and insufficiently tested. The project manager determines that the
equipment meets technology needs.

What skills should the project manager use to obtain team consensus and sponsor approval?


A.
Interpersonal
B. Team-building
C. Stakeholder engagement
D. Leadership

Correct Answer: D