A project manager presents the project scope and deliverables to stakeholders. Two stakeholders disagree about the project scope.
What should the project manager do?


A.
Create a project charter to obtain strategic alignment between the two stakeholders.
B. Update the stakeholder engagement plan to document the concerns.

C. Brainstorm with the stakeholders to clarify requirements.
D. Accommodate the project scope requirements of the more senior stakeholder.

Correct Answer: C