Project Management Professional (PMP) Exam Practice – Question0258

A project manager develops a business case during project initiation. What areas should the project manager consider when developing the business case?


A.
Expected resource performance and cost-benefit analysis
B. Expected resource performance and the project's contribution to the strategic portfolio objectives
C. Business benefits provided by project deliverables and portfolio analysis
D. Business benefits provided by project deliverables and the organizational strategy

Correct Answer: D