After several weeks on a new project, the project manager learns that the accounting department has rejected all charges because the project was not approved. What should the project manager have done to prevent this?


A.
Obtained the funds needed to initiate the project
B. Verified that the business case was authorized by the steering committee
C. Planned the resources necessary to initiate the project
D. Verified that the project charter was authorized by the sponsor

Correct Answer: A