To estimate the cost of project activities for a new project, a project manager uses the schedule from a similar project. What tool or technique is the project manager using?
A. Expert judgment
B. Parametric estimating
C. Bottom-up estimating
D. Analogous estimating
A. Expert judgment
B. Parametric estimating
C. Bottom-up estimating
D. Analogous estimating