Project Management Professional (PMP) Exam Practice – Question0262

To estimate the cost of project activities for a new project, a project manager uses the schedule from a similar project. What tool or technique is the project manager using?


A.
Expert judgment
B. Parametric estimating
C. Bottom-up estimating
D. Analogous estimating

Correct Answer: D