Project Management Professional (PMP) Exam Practice – Question0263

A new project requires resources with specific skills and competencies from various company departments. Since most company staff are already assigned to other projects, the project manager must identify and agree on available internal human resources, and
hire external experts.
What should the project manager use first to obtain resources?


A.
Negotiation skills
B. Acquisition skills
C. Individual and team assessment tools

D. Requirements analysis tools

Correct Answer: B