Project Management Professional (PMP) Exam Practice – Question0267

A project manager decides to conduct a virtual kick-off meeting rather than a face-to-face kick-off meeting. As a result, the project manager fails to gain stakeholder commitment.
What documents should the project manager consult to eliminate similar challenges in the future?


A.
Quality management and stakeholder engagement plans
B. Communications management and stakeholder engagement plans
C. Scope management and communications management plans
D. Project charter and communications management plan

Correct Answer: B