Project Management Professional (PMP) Exam Practice – Question0270

A project manager for a company operating in a competitive market is creating a project scope statement. External limitations are noted.
What is most important to the project sponsor at this stage of the project?


A.
Constraints
B. Deliverables
C. Assumptions
D. Schedule

Correct Answer: C